日本財団 図書館


 

activities need to be not necessarily carried out in dry dock. Those are 16 activities on the network. If an activity on CP can be performed during voyage, time in dry dock can be shorter for certain. We tried to make shorter the time in dock by transferring some activities to OBM. (Scenario 3 in TAB.1).

 

TAB.1 Scenarios for reducing the time in dry dock

Scenario

status

cost performance

0

field data of Past record

 

1

reduction by CPM technique

optiniize tile in dry dock

2

parallel activity introduced

optimize #workers within scheduled time

3

diversion to OBM

cut down dock expenses, reduce tile in dock

 

In Scenario 0 in TAB.1, actual time in dock was 188 hours with the number of workers 234 persons. A simulation analysis was made so as to get the time in dock shorter by increasing the number of OBM workers. CPM technique which minimizes the time to complete the project was combined with the simulation study. CPM is the Critical Path Method, which was originally the production control method. CPM aims at the optimum expenses of work (activity) with restriction that predecessor element (activity) preceded by the successor like PERT technique. In other words, if activity 1 finished, activity 2 starts. if activity 2 finished, activity 3 starts, and so on.

 

As for Scenario 1, the time in dry dock was reduced to 116 hours by 293 workers (see FIG.4). Cost performance was measured for every 10 hour reduction, with the number of workers increased as shown in TAB.2. Dock workers are generally performed sequentially. In some case, dock works are done in parallel. Activity 1 and activity 2 can be performed simultaneously at a distance apart. Generally, works of dry docking is conducted in parallel, say deck, engine and electric division. If deck activities in sequence are switched to parallel activities as much as possible, time in dry dock is much more reduced. As initial time in dry dock was 157 hours with 235 workers, some 'slow moving' activitities were switched to 'fast moving' activities, thus activities on CP was hastened to be 108 hours with 275 workers. This status is called Scenario 2. Cost performance was measured by making time in dock every 10 hours shorter like Scenario 1 in FIG. 3.

 

FIG.4 Cost change due to time in dry dock and the number of workers

Note: Bar charts shows the number of dock workers (use the scale, LHS), graph shows cost(use the scale, RHS). The cost for scenario 3 does not include OBM costs.

 

 

 

前ページ   目次へ   次ページ

 






日本財団図書館は、日本財団が運営しています。

  • 日本財団 THE NIPPON FOUNDATION