Our technical review of the Bond Improvements was limited to the following existing documents:

 

・"Terminal 18 Redevelopment Project. Request for Proposal, Volumes I and II", June 12, 1998, and addenda. Berger/ABAM Engineers, Inc.

・"Harbor Island Conceptual Master Plan Terminal 18" August 22 1996. JWD, Moffatt & Nichol Engineers .

・"Draft Environmental Impact Statement", March 1997. Port of Seattle.

・"Terminal 18 Lease Agreement, Exhibit C", December 17, 1996. Port of Seattle.

・"Design-Build Proposal to Stevedoring Services of America. Inc." September 24 1 998 Morrison Knudsen Corporation.

・"T-18 Intermodal Operations and Capacity, Revised" by Mainline Management, Summer 1998. Port of Seattle.

 

In addition, we reviewed numerous other documents during the course of our analysis of the financial and economic feasibility of the project, including the Bond Resolution, EPC Contract Terminal 18 Lease, Base Lease, Leaseback, Crane Agreement, and Railroad Agreements.

 

We also conducted numerous interviews concerning technical, financial, and market issues, including interviews with individuals from the Port and numerous industry experts.

 

 

 