The UNDP-IMO GEF Project "Removal of Barriers to
the Effective Implementation of Ballast Water Control and
Management Measures in Developing Countries"
18 The status of the above project and steps
planned for its completion were considered under paragraph 25
to 28 below.
Regulations and guidance for their implementation
19 The Chairman recalled the results of previous
considerations by the Working Group regarding the development
of legally binding provisions in the form of
"regulations" and "implementation
guidelines" thereto, ad developed so far (MEPC 41/9,
annexes 1 and 2). Legally binding provisions set out in the
rules would require that these be implemented in accordance
with relevant options set out in the guidelines, or that
prescribed activities shall be carried out taking full
account of the guidelines.
20 The United States experts proposed a number of
revisions to the draft regulations prepared so far. They
further submitted in appendix thereto a"ballast water
management code" replacing the originally planned
"implementation guidelines". The Code comprised
three parts:
Part A Ballast Water Management Practices
Part B Ballast Water Management Plans and Information
Part C Recommendations to assist in implementing the
Appendix.
Parts A and B of the Code would contain mandatory
provisions. whereas Part C was of a recommendatory nature.
21 The United States experts further pointed out that
amendments to the Code annexed or appended to the set of
regulations could; after approval by a two-thirds majority of
Parties present at a meeting, enter into force after a
certain period of time (e.g., 100 days) for all Parties
except those which within that period of time had made a
declaration that they were not able at that stage to accept
the amendment(s). Such a tacit amendment procedure would
ensure that new technical developments and management
procedures could be incorporated without lengthy or
cumbersome amendment arrangements. A precedence for such
framework was IMO's STCW Convention 1978, as amended in 1995,
and the Seafarer's Training, Certification and Watchkeeping
Code (STCW Code).
22 The Working Group agreed to review the previously
developed draft regulations, taking into account the model
introduced by the United States, as well as the
implementation guidance in the form of a Code, which would
provide tools for implementing the regulations. The Working
Group further agreed to use the text of resolution A.868(20)
wherever appropriate in developing,the ballast water
management legislation.
23 The representative from ICS expressed the view
that flag State provisions have to be outlined in a distinct
manner from those addressing port States, if possible through
different instruments. The United States pointed out that the
Working Group should produce one set of legislation
applicable to both flag and port States. This should be
complemented with different options, tools and measures, as
well as recommendations set out in a Code appended to the
regulations. The Chairman noted that the legal framework of
ballast water management provisions would be decided upon by
MEPC 42 in late 1998. In the meantime the Working Group would
follow instructions as reiterated in Assembly resolution
.868(20) regarding the development of a new Amex to MARPOL
73/783. Another lengthy discussion centred around the
question of "deep sea voyages" and ballast water
exchange at "deep sea areas". Even during long
voyages ships may not cross "deep sea areas", e.g.,
from NW Africa to NW Europe. Such conditions would have to be
taken into full account by port States. Other experts
proposed the replacement of "Deep Sea" as defined
in the United States proposal with "High Sea"
according to UNCLOS provisions.
3 The question regarding port State versus flag
State requinrements was raised in various discussions
throughout the meeting of the Working Group.
24 The draft text of a possible annex to MARPOL 73/78
as developed so far by the Working Group is shown in annex 1
to this report. In appendix thereto the proposed (and partly
revised) text for a Ballast Water Management Code has been
set out.
Removal of Barriers to the Effective Implementation of
Ballast Water Control and Management Measures in Developing
Countries
25 A GEF project to assist developing countries in
carrying out efficient ballast water management control
measures had been requested in 1994 by the Ballast Water
Working, and in 1997 was submitted by UNDP to the GEF. After
approval of a PDF Block B project grant in late 1997, IMO
started to execute the project. The project proposal prepared
by IMO had been introduced to the Ballast Water Working Group
at MEPC 40 (MEPC 40/10/2). The activities carried out since
that meeting in executing the project were presented by UNDP
and IMO officers and by the consultants who had been involved
at that stage. The outputs of this project are planned to
include the following:
. 1 a report identifying ballast water
control and management alternatives for developing
countries, and a strategy for removing barriers in order
to allow effective implementation of these measures;
.2 a report summarizing the consequences of
ballast water transfer of exotic species, with an
emphasis on health impacts, particularly on women and
children;
.3 the establishment of selected pilot
demonstration sites, one in each of the world's
development areas, initially confirmed by host countries
and institutions, to test management approaches and
barrier removal mechanisms; and
.4 a full IMO/UNDP/GEF project document which
should incorporate all of the above and outline a
four-year implementation prograrnme.
26 The Working Group recognized that the time
schedule for carrying out the various tasks for completing
the output elements mentioned above was very tight in that a
full project proposal for submission to the GEF Council
meeting in 1998 would have to be completed in July; a Project
Steering Committee has to be established and its first
meeting to be convened in early summer 1998.
27 A report prepared by consultants reflecting the
results of their visits to six developing countries in
different regions of the world was considered by the Working
Group. It was noted that in all these countries a total lack
of control measures regarding ballast water discharges had
been identified. There was also a lack of communication and
co-operation among the involved parties, including research
organizations, co-ordinated by different national
administrative authorities. Poor support existed for
scientific sampling of ballast water proposed for discharge.
In the few cases where sampling was carried out, samples were
taken at random from the surface of the tanks. Analytical
facilities were often at universities situated at a long
distance from port areas.
28 The Working Group welcomed the information
provided on the GEF Ballast Water Project. Several experts
and representatives from port and shipping industries
expressed their continuing willingness to support the project
by providing their expertise and technical advice.
Ballast Water Management Plan
29 The ICS expert informed the Working Group of the
status of development of a model ballast water management
plan which would assist shipowners and others who may be
responsible fro developing an individual ballast water
management plan for an individual ship or a class of ships. A
plan should clearly outline the procedures to be followed and
the records that are to be kept. it should further include a
section on ballast water sampling Identifying sampling points
and access points to tanks where samples could be taken.
30 The Working Group further emphasized the
necessity for maintaining a full and accurate ballast log
reflecting a continuous history of ballast water that has
been taken, in which tanks it had been carried and at which
localities it had been discharged.
31 The Chaiman requested ICS to identify sections of
the Model Ballast Water Management Plan that could form an
appendix to the Code considered under paragraphs 19 to 22
above.
Education and Awareness Material
32 The Working Group was not able to consider this
issue in detail because of lack of time. It welcomed the
videotape submitted by the United States and requested all
members of the Working Group to submit to the next meeting
leaflets and other material prepared in the first instance
for seafarers and personnel of port State authorities.
Information distributed to the wider public would also be
welcome The Working Group would consider the information at
its sessions during MEPC 42 and 43.
Work Programme of the Ballast Water Working Group
33 The Working Group prepared a programme
outlining its tasks covering the period 1998-2000 (MEPC
41/WP.1 O). The Committee agreed in principle, to the
schedule set out in the work programme shown at annex 2 to
this report, subject to further consideration and
confirmation at MEPC 42.
Action requested by the Committee
34 The Committee is invited to approve the report of
the Working Group.on Ballast Water which reflects the results
of its meeting held during MEPC 41.
***
前ページ 目次へ 次ページ