(10) Postponement of investment

Only 46 cars will be introduced in Phase 1. This means that all facilities envisaged in the final plan will not be required immediately. Therefore, construction of some storage tracks and buildings can be postponed to reduce the initial investment.

Ratios of track and buildings for which construction can be postponed will be around:

Buildings: 40% = US$7,436,000

Track: 15% = US$366, 000

Maintenance facilities 35% = US$3,416,000

Namely arround US$ 11,218,000 will be reduced from the initial investment for phase 1.

 

9.3.5 Rail vehicle

 

Table 9.3.5-l summarizes the unit cost of rail vehicle es8mated according to the mndi8ons stated in section 9.2.5.

199-1.gif

 

9.3.6 Summarizing Review

 

Summary of cost review is shown in Table 9.3.6-1. With respect to S5, namely total investment to hardware, JARTS's estimation is about 30% larger than UBTSL's estimation. This difference is caused mainly by difference in cost estimate in civil engineering structures and track.

 

Coments on for difference in cost in civil engineering structures and track have been mentioned in 9.3.2.4 and 9.3.3.4.

 

UBTSL is requested to reconfirm the cost estimates in civil engineering structures and track. With

 

 

 