GAS CARRIERS / LNG
ZEKREET 135,000 m3 type LNG Carrier
Features
1. ZEKREET is the eighth vessel for Qatargas LNG project which is the biggest LNG project to transport six million tons of LNG from Qatar to Japan utilizing ten (10) 135,000 cub.meter LNG carriers.
2. In order to satisfy the "sistership" requirement by the owner / charterer, Mitsui Engineering & Shipbuilding Co., Ltd. (MES) is selected as the "Window Yard" and distributed all design drawings to other members in the consortium i.e.MHI and KHI.
3. Considerable improvement in power requirement is achieved by applying fine hull form and MIPB (Mitsui Integrated Propeller Boss)with reaction rudder.
4. Soft start system utilizing inverter is applied to the cargo pumps, by which the cargo pump starts with gradually increasing voltage to eliminate shock to the liquid piping normally observed at pump start-ups.
5. For contingency, one set of Ship-to-Ship Transfer equipment including the following is supplied to each vessel in the fleet:
・twelve (12) cryogenic flexible hoses (250 mm dia. x 4 m length)
・optical cable for ESDS link
・electric power cable
6. LNG eductor system connected to the partial secondary barrier is replaced with the vaporizer utilizing natural heat transfer.
7. CFD (Computational Fluid Dynamics) is used in actual design scene, such as hull form design and boiler furnace design.
PRINCIPAL PARTICULARS
Length (o.a.) ... 297.50 m
Length (b.p.) ... 283.00 m
Breadth (mld.) ... 45.75 m
Depth (mld.) ... 25.50 m
Draft (mld.) ... 10.95 m
Gross tonnage ... 111,124
Deadweight ... 72,316 T
Main engine ... MHI MS40-2 Steam turbine
MCR ... 26,800 kW x 89 rpm
NOR ... 24,120 kW x 85.9 rpm
Speed (max. trial) ... 21.46 knots
(service) ... 19.52 knots
Complement ... 46
Classification ... NK
Handling gear ...5 t x 20 m x 2 sets, 7 / 2.5 t x 16.5 m x 2 sets
Cargo pump ... 1,200 m3/h x 10 sets
Loading capacity (tank) ... abt. 135,000 m3 (at -163℃, 98.5%).