Schedule for AP227 Edition 2
NWI has been approved by ISO
ARM was finalized at Workshop held from October 11-13, 2000 in Charleston
・ARM is now stable
・will be circulated for review by December 2000
・Final workshop before ballot scheduled for January 9-11, 2001
AIM will be complete by January 2001
CD Ballot planned for March 2001
Summary
AP227 Edition 1
・International Standard (IS)
・Implemented by 3 Process Plant Vendors
AP227 Edition 2 will add capabilities for:
・Piping Shop Fabrication
・Inspection
・Stress and Flow Analysis Inputs
・HVAC
・Cableways
・Consistency with other Ship APs
..Format for GUID
..Defining coordinate reference from Forward and Aft Perpendicular