7 Interlocking Systems and Devices

 

Interlocking devices are used to mutually interlock blocking devices with signal devices, and signal devices with shunting devices, etc. Interlocking devices function as comprehensive safety devices in stations to ensure safe train operation.
The basic safety conditions required of interlocking devices are described below.
Interlocking devices must ensure that:
* All shunts over the route are open and locked in the correct direction.
* The route is not blocked by other trains or cars.
* There are no trains or cars over the route.
* The above locking relationships are secured while the trains are running.

 

In addition, the following overrun protection measures are taken in consideration of the fact that trains may perform improper braking operations and overrun stop signals.
* Protection sections are secured by positioning home signals 100 m or more from the outermost shunt of the station.
* 150 m overrun protection sections or safety sidings are established inside of departure signals for incoming trains.

 

Electric relay interlocking devices are considered to be the ideal interlocking devices for the following reasons due to their superior safety and work efficiency.
* The various locking functions required of interlocking devices can be ensured.
* Multiple routes can be controlled with a short configuration time (approximately 6 seconds) by using electric shunting machines.
* The signal boxes for large stations can be centralized in a single location.
* Operating conditions can be understood with the control panel displays, facilitating route handling.

 

However, with recent advances in electronic technology, electronic interlocking devices which feature computer-based programmed route control (PRC) are tending to be adopted.
When installing interlocking devices, operation planners should take the following items into account to enable the smooth execution of yard work from the viewpoint of the users.
* Methods of using departure and arrival tracks and specification of through tracks (main lines)
* Signal installment positions and overrun protection section ranges and directions
* Confirming the effective length of the track
* Shunting work methods and telecommunication facilities for communication

 

 

 

BACK   CONTENTS   NEXT

 






サイトに関するご意見・ご質問・お問合せ   サイトマップ   個人情報保護

日本財団会長笹川陽平ブログはこちら



ランキング
注目度とは?
成果物アクセスランキング
2,439位
(31,497成果物中)

成果物アクセス数
2,922

集計期間:成果物公開〜現在
更新日: 2019年10月12日

関連する他の成果物

1.REPORT ON THE PRELIMINARY STUDY OF THE PROJECT FOR THE CONSTRUCTION OF A NEW TRANSPORT SYSYTEM IN CAPE TOWN IN THE REPUBLIC OF SOUTH AFRICA
2.タイ国国鉄バンコク?チェンマイ間速度向上計画予備調査報告書
3.PRELIMINARY STUDY ON STATE RAILWAY OF THAILAND NORTHERN LINE TRANSPORT TIME REDUCTION
4.SEMINAR ON MODERNIZATION OF RAILWAY TRANSPORT IN CAMBODIA
5.「海外における鉄道技術セミナーの開催」の報告書
6.平成8年度「高密度輸送の快適化の研究」事業研究報告書
  [ 同じカテゴリの成果物 ]


アンケートにご協力
御願いします

この成果物は
お役に立ちましたか?


とても役に立った
まあまあ
普通
いまいち
全く役に立たなかった


この成果物をどのような
目的でご覧になりましたか?


レポート等の作成の
参考資料として
研究の一助として
関係者として参照した
興味があったので
間違って辿り着いただけ


ご意見・ご感想

ここで入力されたご質問・資料請求には、ご回答できません。






その他・お問い合わせ
ご質問は こちら から