(d) Cooperation in transport with the Thanayong new railway
(e) Cooperation in transport with MRTA Subway
(f) Opening of the Bangkok 2nd Airport
(5) Schedule outline of relevant projects
Table 5.3-1 indicates a rough relation between the period necessary for implementing the time reduction project and scheduled times of the related projects. According to the table, the completion time of the track rehabilitation work until Phitsanulok and the starting time for operating the new train are almost coincided.
Because all of the projects involved are large-scaled, their schedules would be considerably changed. Table 5.3-1 indicates the present progress image when relevant projects will be implemented on the schedule planned at present stage.