(3) Plan for relevant railway construction in Bangkok

 

Subject Outline Reference
Track elevation in bangkok (Hopewell) Elevate the existing SRT line to the second floor and simultaneously construct a new center-Bangkok commuter transport system (normal electric railcar system gauge) and also a expressway will be constructed on 3rd floor as common use Under construction,Phase I is scheduled to be completed in 1998
North-south line:

Between Rangsit and Ponimit

East-west line:

Approx.60 km Hua Mac and Tarinichang                          

Commuter transport in center of Bangkok(Tanyong) Establishment of elevated railway using trunk road spaces in center of Bangkok Under construction,Scheduled to be completed in 1998
Normal electric railcar system of standard gauge
Sukhumbit line:Between Soiwok and North bus terminal,Satohn line:

Approx. 23 km Satohn bridge and National Athletic Stadium

Subway in center of Bangkok(MRTA) Establishment of subway using the underground of trunk roads in the heart of Bangkok Construction contract of first construction area,Scheduled to be completed in 2002
20 km between Ban Sue and Hua Lamphong
Normal electric railcar system of standard gauge
Loan to part of infrastructure construction form Japan

 

 

 

 