Subject |
Outline |
Reference |
Track elevation in bangkok (Hopewell) |
Elevate the existing SRT line to the second floor and simultaneously
construct a new center-Bangkok commuter transport system (normal electric railcar system
gauge) and also a expressway will be constructed on 3rd floor as common use |
Under construction,Phase I is scheduled to be
completed in 1998 |
North-south line: Between Rangsit and Ponimit
East-west line:
Approx.60 km Hua Mac and Tarinichang
|
Commuter transport in center of
Bangkok(Tanyong) |
Establishment of elevated railway using trunk road spaces in center of
Bangkok |
Under construction,Scheduled to be completed in
1998 |
Normal electric railcar system of standard gauge |
Sukhumbit line:Between Soiwok and North bus terminal,Satohn line: Approx.
23 km Satohn bridge and National Athletic Stadium |
Subway in center of Bangkok(MRTA) |
Establishment of subway using the underground of trunk roads in the heart
of Bangkok |
Construction contract of first construction
area,Scheduled to be completed in 2002 |
20 km between Ban Sue and Hua Lamphong |
Normal electric railcar system of standard gauge |
Loan to part of infrastructure construction form Japan |